Underwater Cable Installation

How is it carried out?

Special cabling methods are used in order to carry out installation of underwater connection lines. 

There are 3 types of cabling method that can be used to carry out installation work:

  • Cutter
  • Rotary
  • Hydraulic

 

Cable cutter-layer - this method of cable installation is an analogue of the plow and has very simple design: working riving knife and cutting knife drum onto which the cable is wound, cassettes, roll pins reducing the friction of the cable inside the cassette. The cable cutter is towed during the operation, laying the cable behind it. For example, the schematic below illustrates how this is achieved.

03cfef7a6c7d42d79e32614e9db2ec92

 

The cable cutter operates by the following principle: When moving, the working knife is rakes the soil, forming a trench between the surface of the soil and its wedging part, which reaches a depth of 1.5 meters. A blank cassette is mounted to the rear end of the cable cutter, through which a cable (or multiple cables) is fed, and placed into the trench.

 

Cable cutters can also be self contained, without the need to be towed, as illustrated in the image below.

510f50ce5f5748df8bf8987cbb9a8faf

Different preparations and factors must be accounted for depending on the type of soil that will be encountered during installation of the cable, Such as ploughing and otherwise loosening the soil before the cutter can begin its action. The intensity and scope of the preparatory work depends on the type of soil. It is clear that digging soft soil is easier than rock, and there is a lower chance of running into obstacles in the process.

 

The cable cutter that is used to install underwater cables operates by the same principles. It is necessary to bury the cable around coastal areas in order to prevent mechanical interference from boat anchors, trawls and other human or marine activity. The cable cutter method is used at shallow depths and coastal areas. Conventional underwater cable layer do not form very deep or wide trenches (0.1 - 0.2 m width, 0.7 m depth). The cutter is towed by a barge at a speed of approximately 3 km/h as it moves along the seabed using special runners. A separate control cable is used to monitor the installation process.

 

The Rotary cable layer is a self-propelled rotary excavator trailer truck equipped with a device for loading, transporting and laying of the cable. This type of cable layer is designed for use on thawed and frozen ground. The main operating unit of rotary cable layer is its disc with cutting teeth. This type of cable layer has an operational capacity to dig up to 1km of trench per day.

 

The principal difference between the rotary layer and the cutter is the mechanism by which the trench is dug, illustrated below:

0a702f35687640c9875bc76761023821

 

The established name of the device VHC - Vibrating hydraulic cable-laying, although in fact it is a blade-type device.

HUCL - Hydraulic Underwater Cable-Layer is used to install cables on riverbeds and other water bodies through the use of ships or vessels. The main operating part of this mechanism is the hydraulic borax, which is a hose based mechanism mounted on the vessel. The hose is used to feed a stream of pressurized water, which acts as a drill, loosening the ground forming a trench into which the cable is placed.

It is worth remembering that cables only need to be entrenched in shallow waters or small bodies of water. In the ocean, where depths can reach up to 8km; the cable is simply placed on the ocean floor where only sea water and pressure can pose a threat (with the unlikely exception of unexpected seismic activity).

Small water bodies

Small water bodies include streams, small lakes, narrow swamps and rivers (including mountain rivers).

For water bodies of a depth of less than 0.8m, no specialized underwater  equipment is required, and the track can be made using conventional methods. Only small water bodies of 0.8m - 6.0m require the use of underwater cable layers.

Before installation can begin, the following preparations must be made:

• Shaving off and smoothing of coastal slopes by bulldozer or excavator to ensure a smooth descent and exit of the cable laying vehicle from water
• launder jetting of obstacles discovered during underwater surveys in order to remove them from the path;
• two or threefold ploughing of the ground on the planned route;
• Checking the waterproofing and structural integrity of the cable with the use of excess pressurized air. Testing cores by passing current;
• Loading the cable onto the cable laying vessel and moving to the site of operation.

In order to run the cable laying vessel through narrow bodies of water (less than 300m in width); a tractor column is used.

Environmental conditions in the area of installation can play a significant role in the installation process. For example, freezing of the water body and the formation of a sheet of ice thick enough to accommodate people and wheel-tracked equipment can greatly facilitate the process of installation. If the segment required the use of a cable laying vessel (Distance of 400m or more), the workers can dig a lane in the ice through which the cable can be lowered into the trench at the bottom.

 

Cabling to the bottom using a vessel

 

Installation of cables across narrow rivers can be achieved with the use of mechanized equipment located on the other side of the river bank. However, in areas where this is not possible, such as coastal areas, wide rivers and open waters; the use of cable laying barges or vessels is required.

 

Hydraulic cable layers are the go to option in this scenario. This is due to the fact that soil located underwater is more supple than ice or hard soil, therefore a jet of pressurized water is sufficient enough to create a trench for the subsequent installation of the cable.

 

As stated previously, cables require entrenchment at depths of 1500m - 2000m due to possible interference from factors such as fishing activities and boat anchors. In such situations, the cutting-layer method can be used, or alternatively, a large plow can simply be lowered onto the seabed and dragged by the vessel, creating a sufficient trench in order to protect the cable from fishing gear and other interference. At greater depths, the heavily armored cable can simply be laid on the seabed as the depth alone is enough to protect the cable from such factors.


1aedaa71d0cd46cfa29323a7b380cb87

An example of a plow used in creating the trench. With an estimated working depth of 2,000 meters

While a single strand of cable can be used when carrying out installation in small bodies of water due to the distances being relatively small. The distances at sea are much larger, and the length of a single strand of cable is limited to the capacity of the drum. In addition to this, the signal transmission can be interfered with via distortion of the cable by tidal waves, leading to loss in the strength of the signal.   To compensate for these losses, signal repeaters and amplifiers are used in areas where cables require to be linked and areas of signal loss. This allows the signal to be transmitted over longer distances without losses occuring. Repeaters and amplifiers are typically placed 150km apart.

Pictured below is a partially disassembled signal amplifier prior to installation:

846308ef5fae1d98d4c228640669d8d9

Signal amplifier shown ready for installation:

99d703a3b308435c8980063f67cc1b37

 

As mentioned above, signal amplifiers are attached at a frequency of every 150km. Industrial underwater cables are manufactured at lengths between 5 - 25km, which is significantly less than the distance placement of the amplifiers. In these cases, the end of the drum is connected to another one via a connection box (Pictured below):

 

14521faa3bd24ef3b1a7f764e20adf51

 

Disassembled connection box:

 

1fc5e115936e4b98b8a44a6d80b1a15f

In the event of a breakage, the concept behind carrying out repairs is relatively simple. However due to the conditions under which the installation is carried out; the task itself can prove quite difficult. The vessel lifts the damaged end of the cable, which is then attached to a buoy. A trawl is then used to lift the other part of the cable. The area which was penetrated by water under pressure is cut off and a spare replacement cable segment is attached in its place.